Identify required approvals
Request the supplier’s authorized onboarding process, account lead time, credit requirements, ordering method and cutoff. Compare those dates with key material requirements.
Run a dated supply scenario
A buyer needs materials 18 days after closing. Account setup takes 10 days and delivery takes 12 after order. Identify a four-day gap and evaluate whether previously authorized orders or temporary stock can cover it.
Assign continuity checks
Have the deal team approve correspondence and responsibilities. Verify the first test order, delivery promise and approved payment setup before treating the dependency as resolved.
Buyer Checklist
- List essential suppliers
- Confirm lead times
- Model the readiness gap
- Verify first-order ownership
Frequently Asked Questions
Is an approved application enough to show readiness?
Confirm the supplier can accept the buyer’s order under the documented terms and provide a delivery date.