Build a project-level view
Capture contract amount, approved changes, billed and collected amounts, actual cost and estimated cost to finish. Note disputed scope and missing acceptance evidence.
Test the remaining margin
A fictional job has a $200,000 contract and $150,000 billed. A review identifies $65,000 in remaining cost and $45,000 previously spent. The job may have positive overall margin, while its remaining $50,000 billable amount trails the $65,000 future cost.
Align financial and operating views
Have the diligence accountant review reporting treatment. Ask the project owner to verify staffing, materials and remaining approval dates before relying on the cash forecast.
Buyer Checklist
- Collect approved scope
- Reconcile billings and costs
- Test cost to complete
- Confirm operating ownership
Frequently Asked Questions
Is billed percentage a substitute for work completed?
Billing follows the agreement. Verify progress and remaining work separately.